Accept owners and dates
Which suggested owners have accepted which tasks? Confirm current review dates and the invitation/portal submission deadline.
ANRF · MAHA LEAPFROG
ANRF TRACK B · VERIFIED 4 OCT 2026
Current actions, evidence and decisions for the IAIRO contribution.
| Task & next action | Assignment | Dependency & date | Status & source |
|---|---|---|---|
Record invitation/portal deadline and adopt current review/upload/submission dates. Critical priority | No accepted assigneeSuggested: Vimal Mishra | Invitation or portal notice Due: Unconfirmed | To doVerified: 4 Oct 2026Full working proposal v1 · Cover; A3Source |
Obtain IITGN acceptance of the proposed ₹5 crore ANRF allocation and a written recipient/payment route; scientific co-lead status does not establish grant-recipient or account authority. Critical priority | No accepted assigneeSuggested: IITGN Grants/Finance + Vimal Mishra; IAIRO Finance | Institution-wise budget; sanction conditions; IAIRO status Due: Unconfirmed | WaitingVerified: 4 Oct 2026Claude budget v10_MAINTENANCE · reviewed 4 Oct 2026 |
Simplified agreement revision in progress. Compare the Oct3 10-page Library review draft with the local Oct2 discussion v2; finish Schedule B allocation, maintenance and finance terms and reconcile five researchers with the 13-person budget before institutional review and authorised signatures. Critical priority | No accepted assigneeSuggested: IITGN/IAIRO legal + proposal coordinator | General signed MoU clause 3(l); approved schedules; both institutional clearances Due: Unconfirmed | In progressVerified: 4 Oct 2026Oct3 Library review draft + Oct2 local discussion v2; update instruction 4 Oct |
Record competent-authority approval and exact permitted source mapping for ₹5 crore / ₹1 crore annually. No approved amendment or source allocation has been found. Critical priority | No accepted assigneeSuggested: IAIRO Finance + Hitesh/Niyati | Source sanctions and approval references Due: Unconfirmed | WaitingVerified: 4 Oct 2026Source-funding audit and unsigned commitment letter; reviewed 4 Oct |
Map source sanctions to each AIRO budget head/year. MeitY AA Annex II.15 needs prior approval for other assistance for this project; II.16 limits entrusting funded implementation/diverting grant aid. Do not presume a blanket NOC for unrelated separate work. ANRF receipts are not automatically private match; prior Doot exemption claims were withdrawn. Critical priority | No accepted assigneeSuggested: Hitesh/Niyati + IAIRO Finance | Detailed DST sanction; MeitY scope and permissions; signed matching definitions Due: Unconfirmed | WaitingVerified: 4 Oct 2026Completed source-funding and Claude Doot route audits; reviewed 4 Oct |
Reconcile v10 head/year table into the proposal and Schedule B: ₹5 crore requested ANRF + ₹5 crore IAIRO; 3 postdocs, 5 engineers, 1 coordinator and 4 PhD researchers. Obtain IITGN acceptance, institutional approval and portal-format annexure. Keep the ₹20 crore consortium total separate. Critical priority | No accepted assigneeSuggested: IAIRO Finance + Amit Sheth; IITGN Finance | IAIRO-04; source mapping; rates, overhead and taxes Due: Unconfirmed | ReviewVerified: 4 Oct 2026Claude budget v10_MAINTENANCE · reviewed 4 Oct 2026 |
Deliver the historical Ukai screen, Gujarati/English explanations, uncertainty/drivers, measured latency and documented operator review count/comments. Proposed description is not the prototype. Critical priority | No accepted assigneeSuggested: Amit Sheth | PR1 forecast outputs; PR3 historical operation outputs; Ukai operator reviewers Due: Unconfirmed | To doVerified: 4 Oct 2026AIRO_ANRF_Leapfrog_Full_Proposal_Template_v1-2.docx · 5.1 What the preliminary results must showSource |
Joint IITGN/IAIRO hosting; Amit Sheth is risk owner. v10 illustrates ₹171.23324 lakh for Y6–10, outside the ₹10 crore funded slice and unchanged ₹5 crore cash commitment. Decide funding source, institution split, custodian, staffing, service scope and continuity; no 50:50 split is evidenced. Five years is the proposal commitment; FAQ38 requires a plan without prescribing duration. Critical priority | No accepted assigneeSuggested: Amit Sheth (risk owner) + IITGN/IAIRO Finance | Schedule B; institutional approvals; source availability; service plan Due: Unconfirmed | WaitingVerified: 4 Oct 2026Claude budget v10_MAINTENANCE · reviewed 4 Oct 2026; ANRF FAQ38 |
Which suggested owners have accepted which tasks? Confirm current review dates and the invitation/portal submission deadline.
Which permitted sources will cover IAIRO ₹5 crore cash, and will IITGN accept the proposed ₹5 crore ANRF allocation?
Agree source, institutional split, service scope and custodian for joint hosting and the illustrative Y6–10 maintenance plan.
Select the proposal master; review the simplified agreement when available and complete its financial/maintenance schedules.
Choose the transfer-test site, field/milestone sequence and numeric KPI thresholds with technical leads.